The ten activities specified below are to be performed to make a product. Then answer the given
subquestions.
What is the balance delay for the line (or lines) identified in the main question?
(Enter your answer in % rounded to two decimal places, without the percentage symbol. Eg. If you
compute the answer as 0.10005, then enter 10.01 as your answer)
A published solution is not available for this question yet.
Currently, a company is using a layout which consists of 9 workstations. 200 sandwiches are
produced in a day on this layout. A typical day consists of a single shift which runs for 10 hours.
The sandwich-making process consists of 9 activities (the information is provided in the table
below).
What is the current efficiency of the line where each activity is performed on a separate
workstation (enter only the numerical value up to two decimal places without the “%” symbol.
Example: if the answer is 99.756%” enter only “99.76”)?
A published solution is not available for this question yet.
Sky Airlines has to decide its plan for allowing booking a flight between Chennai and Bengaluru.
The aircraft has a capacity of 100 (identical seats). The price for economy passengers is INR 1000
per seat whereas for business passengers it is INR 5000 per seat. If the demand for business
passengers is uniformly distributed between [10,40], what is the protection level?
6406531887354.
34
6406531887355.
32
6406531887356.
68
6406531887357.
70
A published solution is not available for this question yet.
Match the following columns by selecting the correct name from Column B for the labels in
column A which are depicted in the ‘**Figure: EOQ model**’ below:
Pranjal is shopping in a departmental store. He has a list of items which he prepared at home
itself. He picked a few packets of tea as part of his list. He could see coffee packets and milk-
powder packets on the neighbouring shelves. He picked a few milk-powder packets. However,
these were not part of his list. He was searching for Good-day biscuits. He could identify only one
packet on the shelf. However, there were a lot of Sun-feast biscuits lying on the next shelf. So, he
picked ten Sun-feast packets. Now map the scenarios with the items below:
6406531887377.
P1-S1, P2-S3, P3-S4
6406531887378.
P1-S2, P2-S1, P3-S3
6406531887379.
P1-S2, P2-S1, P3-S4
A published solution is not available for this question yet.
Limat Ltd. wants to determine its order quantity for one of its components. The annual
consumption for the component is 80,000 units and its purchasing price is Rs. 50 per unit. The cost
of placing an order is Rs. 1,200 and carrying cost per unit is 6% of the purchasing price.
Based on the above data, answer the given subquestions.
Calculate the Economic Order Quantity (EOQ).
A published solution is not available for this question yet.
Limat Ltd. wants to determine its order quantity for one of its components. The annual
consumption for the component is 80,000 units and its purchasing price is Rs. 50 per unit. The cost
of placing an order is Rs. 1,200 and carrying cost per unit is 6% of the purchasing price.
Based on the above data, answer the given subquestions.
Calculate the number of orders per year.
A published solution is not available for this question yet.
Limat Ltd. wants to determine its order quantity for one of its components. The annual
consumption for the component is 80,000 units and its purchasing price is Rs. 50 per unit. The cost
of placing an order is Rs. 1,200 and carrying cost per unit is 6% of the purchasing price.
Based on the above data, answer the given subquestions.
Calculate the annual order cost.
A published solution is not available for this question yet.
Limat Ltd. wants to determine its order quantity for one of its components. The annual
consumption for the component is 80,000 units and its purchasing price is Rs. 50 per unit. The cost
of placing an order is Rs. 1,200 and carrying cost per unit is 6% of the purchasing price.
Based on the above data, answer the given subquestions.
Calculate the annual inventory carrying cost.
A published solution is not available for this question yet.
Which of the following is/are considered in the Vehicle Routing Problem but not considered in
TSP?
6406531887390.
Subtour elimination
6406531887391.
Any capacity restrictions
6406531887392.
A specific starting point
6406531887393.
Multiple salesman
**SPG**
**Section Id :** 64065338349
**Section Number :** 2
**Section type :** Online
**Mandatory or Optional :** Mandatory
**Number of Questions :** 36
**Number of Questions to be attempted :** 36
**Section Marks :** 50
**Display Number Panel :** Yes
**Group All Questions :** No
**Enable Mark as Answered Mark for Review and**
Yes
**Clear Response :**
**Maximum Instruction Time :** 0
A published solution is not available for this question yet.