Question 348 NAT · 2.0 marks
Now, suppose BA realizes that the fixed costs per flight are in fact 41000 instead of 30000. It also
finds out that two different types of passengers fly to Chennai. Type A consists of business people
with a demand of QA = 260 - 0.4P and type B consists of students with a demand of QB= 240 - 0.6P.
BA decides to charge these two types different prices.
A published solution is not available for this question yet.
Pranjal is shopping in a departmental store. He has a list of items which he prepared at home
itself. He picked a few packets of tea as part of his list. He could see coffee packets and milk-
powder packets in the neighbouring shelves. He picked a few milk-powder packets, however these
are not part of his list. He was searching for Good-day biscuits. He could identify only one packet in
the shelf remaining. However, there were lot of Sun-fist biscuits lying in the next shelf. So he
picked ten Sun- fist packets. Now map the scenarios with the items below:
6406533045332.
P1-S1, P2-S3, P3-S4
6406533045333.
P1-S2, P2-S1, P3-S3
6406533045334.
P1-S2, P2-S1, P3-S4
A published solution is not available for this question yet.
Ashoke motors manufactures micro-cars in Pune plant. It sources various parts for a car from its
different plants located across India and also from its subcontractors. The Pune plant assembles
the final product. For assembling, different machines are involved. On 3\(^{rd}\) of August, one of the
machine caught fire and the entire assembly line stopped until a substitute machine arrived. What
type of facility layout Ashoke Motors is maintaining at the Pune Plant?
6406533045299.
Product layout
6406533045300.
Process layout
6406533045301.
Fixed position layout
A published solution is not available for this question yet.
A factory works for two 8-hour shifts each day and produces a total of 24,000 electric bulbs using a
set of workstations. There are 8 activities required to manufacture the bulb, such that the sum of
all activity times is equal to 12 seconds. How many workstations are required to main the specified
level of production (assuming that activities can be combined into those workstations in any order)
(enter your answer in numeric value)?
A published solution is not available for this question yet.
There are four demand points at A(1,2), B(2,3), C(3,5), D(4,1). The respective demand at these
points are 7, 1, 3, 5. Select the optimal location based on cross-median approach.
6406533045304.
(2,2)
6406533045305.
(3,2)
6406533045306.
(2.5,2)
6406533045307.
(2,3)
A published solution is not available for this question yet.
A contractor estimates that the size of the workforce needed over the next 5 weeks is 5, 7, 8, 4 and
6 workers, respectively. Excess labour kept on the force will cost $300 per worker per week, and
new hiring in any week will incur a fixed cost of $400 plus @200 per worker per week. The
objective is to minimize the total cost of labour needed for the project. If Dynamic Programming is
applied to this problem, answer the given subquestions:
How is a stage represented by?
6406533045312.
Week
6406533045313.
Number of labours available in a week
6406533045314.
Number of new hires in a week
6406533045315.
Total cost of labour in a week.
A published solution is not available for this question yet.
A contractor estimates that the size of the workforce needed over the next 5 weeks is 5, 7, 8, 4 and
6 workers, respectively. Excess labour kept on the force will cost $300 per worker per week, and
new hiring in any week will incur a fixed cost of $400 plus @200 per worker per week. The
objective is to minimize the total cost of labour needed for the project. If Dynamic Programming is
applied to this problem, answer the given subquestions:
What are the alternatives in a stage?
6406533045316.
Week
6406533045317.
Number of new hires in a week
6406533045318.
Number of labours in a week
6406533045319.
Number of labours available at the end of previous week
6406533045320.
Total cost of labour in a week.
A published solution is not available for this question yet.
A contractor estimates that the size of the workforce needed over the next 5 weeks is 5, 7, 8, 4 and
6 workers, respectively. Excess labour kept on the force will cost $300 per worker per week, and
new hiring in any week will incur a fixed cost of $400 plus @200 per worker per week. The
objective is to minimize the total cost of labour needed for the project. If Dynamic Programming is
applied to this problem, answer the given subquestions:
How state variable is defined for this problem?
6406533045321.
Week
6406533045322.
Number of labours in a week
6406533045323.
Number of labours available at the end of previous week
6406533045324.
Number of new hires in a week
6406533045325.
Total cost of labour in a week.
A published solution is not available for this question yet.
A contractor estimates that the size of the workforce needed over the next 5 weeks is 5, 7, 8, 4 and
6 workers, respectively. Excess labour kept on the force will cost $300 per worker per week, and
new hiring in any week will incur a fixed cost of $400 plus @200 per worker per week. The
objective is to minimize the total cost of labour needed for the project. If Dynamic Programming is
applied to this problem, answer the given subquestions:
What is the optimal solution (objective function value) in Stage 5 when the state variable takes
value 4?
A published solution is not available for this question yet.
Bluescope company estimates its ordering cost at Rs 400 and carrying cost to be Rs.2/year/unit.
The estimated annual requirement is 10,000 units at a unit price of Rs. 10. Calculate the given
subquestions:
What is the economic order quantity (EOQ)?
A published solution is not available for this question yet.
Bluescope company estimates its ordering cost at Rs 400 and carrying cost to be Rs.2/year/unit.
The estimated annual requirement is 10,000 units at a unit price of Rs. 10. Calculate the given
subquestions:
Calculate the number of orders per year.
A published solution is not available for this question yet.
Bluescope company estimates its ordering cost at Rs 400 and carrying cost to be Rs.2/year/unit.
The estimated annual requirement is 10,000 units at a unit price of Rs. 10. Calculate the given
subquestions:
Calculate the annual inventory carrying cost.
A published solution is not available for this question yet.
Bluescope company estimates its ordering cost at Rs 400 and carrying cost to be Rs.2/year/unit.
The estimated annual requirement is 10,000 units at a unit price of Rs. 10. Calculate the given
subquestions:
While rechecked, Bluescope company finds that the order cost should have been 20% more than
the currently estimated value. What should be the percentage increase in the EOQ in this case?
Enter your answer without the ‘%’ symbol.
A published solution is not available for this question yet.
Colony Shop is stocking heavy coats for next winter. Colony pays $50 for coat and sells it for $110.
At the end of the winter season, Colony Shop offers the coats at $55 each. The demand for coats
during the winter season is more than 20 but less than or equal to 30, all with equal probabilities.
Determine the optimal order quantity that will maximize revenue for Colony Shop. Consider
demand to be continuous.
A published solution is not available for this question yet.
You visit the car service centre to get your car washed. In the service centre, washing done using
automated systems, e.g. the car is put on a moving belt, water is sprayed, drying is also done.
Which of the following term represents this scenario?
6406533045354.
Digitization
6406533045355.
Automation
6406533045356.
Digital transformation
A published solution is not available for this question yet.
Suppose you need to accept reservation for a flight. There are total 100 seats in the aircraft. You
have two classes of passengers - economy and business. One economy seat gets you 2,500 Rs of
revenue while a business seat gets 7,500 Rs. From your experience, you know the demand for
business travellers follows a uniform distribution in [10,40]. Then answer the given subquestions:
What is the Booking limit?
A published solution is not available for this question yet.
Suppose you need to accept reservation for a flight. There are total 100 seats in the aircraft. You
have two classes of passengers - economy and business. One economy seat gets you 2,500 Rs of
revenue while a business seat gets 7,500 Rs. From your experience, you know the demand for
business travellers follows a uniform distribution in [10,40]. Then answer the given subquestions:
What is the protection level?
A published solution is not available for this question yet.