Questions and published explanations below are available without starting a test. Some questions may not have a published solution yet.
14 / 15 published solutions
Question 2 MCQ · 2.0 marks
Pranjal is shopping in a departmental store. He has a list of items which he prepared at home
itself. He picked a few packets of tea as part of his list. He could see coffee packets and milk-
powder packets in the neighbouring shelves. He picked a few milk-powder packets, however these
are not part of his list. He was searching for Good-day biscuits. He could identify only one packet in
the shelf remaining. However, there were lot of Sun-fist biscuits lying in the next shelf. So he
picked ten Sun-fist packets. Now map the scenarios with the items below:
6406536374069.
P1-S1, P2-S3, P3-S4
6406536374070.
P1-S2, P2-S1, P3-S3
6406536374071.
P1-S2, P2-S1, P3-S4
Published solution
**1. Classify the product relationship P1:** Tea and coffee can satisfy a similar beverage need, so P1 maps to S2, substitution.
**2. Classify P2:** Milk powder can be consumed together with tea, so P2 maps to S1, complementary products. Its unplanned purchase may also involve impulse buying, but the table asks for the product-pair relationship.
**3. Explain the biscuit switch P3:** Limited Good-day stock leads Pranjal to buy the available Sun-fist brand. His observed purchase depends on shelf inventory, so P3 maps to S3, inventory-dependent demand.
**Answer: B — P1–S2, P2–S1, P3–S3.**
A: **Incorrect:** Tea/coffee are not the intended complementary pair, and the other two mappings do not match the scenario.
B: **Correct:** It gives P1–S2, P2–S1 and P3–S3.
C: **Incorrect:** The biscuit switch is attributed to stock availability rather than an unexplained impulse.
A factory works for two 8-hour shifts each day and produces a total of 30,000 electric bulbs using a
set of workstations. There are 8 activities required to manufacture the bulb, such that the sum of
all activity times is equal to 12 seconds.
Based on the above data, answer the given subquestions.
What is the cycle time (in seconds) at any workstations?
(round your answer to one decimal)
Published solution
**1. Convert daily operating time:** Two 8-hour shifts provide \(T=2(8)(3600)=57{,}600\) seconds per day.
**2. Divide time by required output:** \[C=\frac{T}{Q}=\frac{57{,}600}{30{,}000}=1.92\text{ seconds/unit}.\]
**3. Apply the requested rounding:** The required line cycle time is 1.9 seconds to one decimal. This is the permitted interval between completed bulbs, not the sum of all task times.
**Answer: 1.9.**
A factory works for two 8-hour shifts each day and produces a total of 30,000 electric bulbs using a
set of workstations. There are 8 activities required to manufacture the bulb, such that the sum of
all activity times is equal to 12 seconds.
Based on the above data, answer the given subquestions.
What is the theoretical minimum number of workstations required?
Published solution
**1. Compute the unrounded cycle time:** \(C=57{,}600/30{,}000=1.92\) seconds per bulb. Retain this value while calculating the station requirement.
**2. Divide total work by cycle time:** \[N_{\min}=\left\lceil\frac{\sum t_i}{C}\right\rceil=\left\lceil\frac{12}{1.92}\right\rceil=\lceil6.25\rceil=7.\]
**3. Interpret the bound:** A fraction of a workstation is not allowed, so round upward. Seven is a theoretical lower bound; individual task times and precedence can require more stations.
**Answer: 7.**
Identify the examples for Offshoring from the list below:
6406536374074.
Micron Technology, a US based semiconductor giant, setting up a Supply
Chain Analytics team, in India.
6406536374075.
Micron signs an agreement with Taiwan based TSMC Co., to manufacture
silicon wafer for their ICs.
6406536374076.
Western Australia’s electricity network agency assigns Tata Consultancy
Services at Pune, to support it with an overhaul of its legacy IT systems, aimed at delivering
cheaper and more reliable power.
6406536374077.
Tata Motors assigns the manufacturing of its braking system to TACO group.
A published solution is not available for this question yet.
Optimal solution in a facility location problem using Euclidean method will
result in a region
6406536374080.
Optimal solution in a facility location problem using Euclidean method rarely
matches the center of gravity
6406536374081.
Optimal solution in a facility location problem using Euclidean method will
result in a point
6406536374082.
Optimal solution in a facility location problem using Euclidean method
matches the center of gravity in not of the cases
Published solution
**1. Identify the distance objective:** The usual Euclidean location problem minimizes weighted straight-line distances: \[\min_{x,y}\sum_i w_i\sqrt{(x-x_i)^2+(y-y_i)^2}.\] Its solution is a weighted geometric median.
**2. Distinguish the center of gravity:** A weighted coordinate mean minimizes the sum of squared distances, a different objective. It can coincide with a geometric median in symmetric cases, but equality is not guaranteed.
**3. Interpret the standard result:** A nondegenerate Euclidean problem generally identifies a particular optimal point, rather than the median interval/rectangle possible with rectilinear distance.
**Answer: B, C — B and C — generally a point, not generally the center of gravity.**
**Convention note:** The question uses “rarely” informally. Coincidence depends on the data, and special collinear configurations can have an interval of minimizers. The answer assumes the usual unsquared Euclidean objective and a nondegenerate instance.
A: **Incorrect:** A region is not the usual nondegenerate Euclidean-location result, though special collinear cases can have multiple optimal points.
B: **Correct:** Read as “does not generally coincide”: a geometric median is not generally the weighted coordinate mean.
C: **Correct:** A point is the standard nondegenerate result; this is not a uniqueness theorem for every possible dataset.
D: **Incorrect:** If the malformed phrase means “none,” it is false because symmetry can produce coincidence; if it means “most,” that is not generally guaranteed.
Which of the following is an advantage of Process Layout?
6406536374113.
Low material handling
6406536374114.
Total production time per unit is small
6406536374115.
Low training cost for the operators
6406536374116.
It can accommodate high variety of products
Published solution
**1. Identify a process layout:** Similar equipment or functions are grouped together, and each job follows the departments needed for its own processing requirements.
**2. Identify the principal advantage:** Different products can follow different routes, giving flexibility for high variety and lower-volume production. This flexibility typically brings more handling, scheduling and operator-skill requirements.
**Answer: D — It can accommodate high variety of products.**
A: **Incorrect:** Variable routing generally increases material movement relative to a dedicated flow line.
B: **Incorrect:** Queues, moves and different routes can lengthen throughput time.
C: **Incorrect:** General-purpose equipment and varied jobs usually require skilled operators and substantial training.
D: **Correct:** Flexible routing can accommodate many different product types.
Rana Bakery, a company is using a layout which consists of 9 workstations. 200 sandwiches are
produced in a day on this layout. A typical day consists of a single shift which runs for 10 hours.
The sandwich-making process consists of 9 activities (the information is provided in the table
below).
What is the current efficiency of the line where each activity is performed on a separate
workstation (Enter only the numerical value up to two decimal places without the “%” symbol.
Example: if the answer is 99.756%” enter only “99.76”)?
Published solution
**1. Sum the work content:** The nine task times are 20, 10, 60, 40, 20, 5, 5, 15 and 5 seconds, totaling 180 seconds per sandwich.
**2. Use the stated operating output:** A 10-hour day provides 36,000 seconds. At 200 sandwiches/day, the observed cycle interval is \(C=36{,}000/200=180\) seconds.
**3. Calculate utilization against the stated pace:** With nine stations, \[\eta=\frac{\sum t_i}{NC}\times100=\frac{180}{9(180)}\times100=11.11\%.\] Enter 11.11 without the percent sign.
**Answer: 11.11.**
**Convention note:** This uses the stated actual output of 200/day. If the question instead asks theoretical line-balancing efficiency at full bottleneck capacity, the longest station takes 60 seconds, giving 180/(9×60)=33.33%. The key’s 11–12 range uses the observed-output interpretation.
The Production rate of an assembly line is determined by its
6406536374083.
Slowest station
6406536374084.
Fastest station
6406536374085.
Idle station
6406536374086.
None of these
Published solution
**1. Find the bottleneck:** Each unit must pass through the required stations. The station with the longest effective processing time cannot supply units as quickly as the others.
**2. Convert its time into a rate:** For a simple serial line without parallel capacity, \(\text{maximum rate}=1/\max_i t_i\). Faster stations cannot remove that bottleneck merely by working faster.
**Answer: A — Slowest station.**
A: **Correct:** Its effective capacity limits the serial line’s sustainable throughput.
B: **Incorrect:** A fast station can finish early but must wait for the bottleneck.
C: **Incorrect:** An idle station is not the normal capacity-setting rule.
D: **Incorrect:** The bottleneck station is already identified by A.
Which of the following is an advantage of Product Layout?
6406536374087.
It can accommodate high variety of products
6406536374088.
Small in-process inventory
6406536374089.
High utilization of machines
6406536374090.
Low investment
Published solution
**1. Identify a product layout:** Workstations follow the fixed processing sequence for a standardized product.
**2. Explain the inventory benefit:** A balanced, repetitive flow reduces movement and waiting between operations, helping keep work in process small. It does not guarantee low investment or high utilization under every demand level.
**Answer: B — Small in-process inventory.**
A: **Incorrect:** High variety generally favors a flexible process layout rather than a dedicated line.
B: **Correct:** Continuous, coordinated flow can reduce intermediate queues and work in process.
C: **Incorrect:** Utilization depends on demand and line balance; it is not guaranteed for all dedicated machines.
D: **Incorrect:** Dedicated lines can require substantial initial investment.
Select the appropriate layout for Quadrants A, B, D in the following figure:
6406536374091.
A: Group layout, B: Product layout , D: Process layout
6406536374092.
A: Product layout, B: Process layout , D: Group layout
6406536374093.
A: Process layout, B:Group layout , D: Product layout
Published solution
**1. Read the axes:** Variety rises upward and volume rises to the right. Thus A is high-variety/low-volume, B is high-variety/high-volume, and D is low-variety/high-volume.
**2. Match the layout choices:** A needs process-layout flexibility. B uses the question’s group/cellular compromise, organizing related product families. D favors a dedicated product flow line.
**Answer: C — A: Process; B: Group; D: Product.**
**Convention note:** The diagram is a simplified classification. Cellular/group layouts usually serve product families at intermediate variety and volume; the quadrant labels are interpreted within this figure.
A: **Incorrect:** It places a product line in the high-variety quadrant and a process layout in the low-variety/high-volume quadrant.
B: **Incorrect:** It assigns a product line to low volume/high variety and misses the high-volume/low-variety product quadrant.
C: **Correct:** It gives A=Process, B=Group and D=Product, matching the displayed framework.
Following is the layout from an aircraft manufacturing company. Identify the layout from the
figure below.
6406536374094.
Product layout
6406536374095.
Process Layout
6406536374096.
Group layout
6406536374097.
Fixed position layout.
Published solution
**1. Identify the intended production setting:** Aircraft assembly involves a large, heavy product for which moving every partially assembled unit through small functional departments can be impractical.
**2. Apply the fixed-position principle:** The aircraft stays at its assembly position while workers, tools and components are brought to it. This is the fixed-position layout intended by the question.
**Answer: D — Fixed position layout..**
**Convention note:** The campus-style image labels functional buildings and does not itself prove that every aircraft operation is stationary. Real aircraft plants can combine layouts; D is the intended final-assembly classification.
A: **Incorrect:** A product layout moves work through a fixed sequence of stations; it is not the intended stationary-aircraft arrangement.
B: **Incorrect:** A process layout groups similar functions and routes jobs between them.
C: **Incorrect:** A group layout organizes resources into cells for product families.
D: **Correct:** The large aircraft remains in place while resources come to the assembly location.
Identify the Industry 4.0 version of transportation.
6406536374098.
IC engine
6406536374099.
Electric car
6406536374100.
Hyperloop
Published solution
**1. Identify the course’s advanced-transport example:** Hyperloop proposes high-speed movement of pods through low-pressure tubes, combining advanced propulsion, controls and infrastructure.
**2. Match the offered choices:** Within this course’s historical examples, Hyperloop is the intended Industry 4.0 transport concept. An internal-combustion engine and an electric drivetrain alone do not define digitally connected transport.
**Answer: C — Hyperloop.**
**Convention note:** This is a course-specific example, not a universal technical definition of Industry 4.0. Connected, data-driven and autonomous systems can also be Industry 4.0 transport applications; an electric vehicle can incorporate them.
A: **Incorrect:** The internal-combustion engine is an earlier industrial transport technology.
B: **Incorrect:** Electric propulsion alone is not the course’s intended marker for Industry 4.0.
C: **Correct:** Hyperloop is the advanced transport concept intended in this question.
Select the layout which do not require general supervision:
6406536374101.
Product layout
6406536374102.
Process layout
6406536374103.
Group layout
6406536374104.
Fixed position layout
Published solution
**1. Interpret the supervision distinction:** A process layout groups similar machines or operations into functional departments. Each department can be supervised by a specialist in that process.
**2. Identify the intended answer:** This enables specialized/functional supervision rather than relying only on one general supervisor across unlike operations. It does not eliminate supervision.
**Answer: B — Process layout.**
**Convention note:** Read “do not require general supervision” as “permit specialized functional supervision.” A process layout still requires supervision and can be demanding to schedule.
A: **Incorrect:** A flow line still needs line coordination and supervision; it is not the functional-supervision answer sought.
B: **Correct:** Grouping like processes supports specialized departmental supervision.
C: **Incorrect:** Cells may support team supervision, but this is not the course’s intended functional-layout distinction.
D: **Incorrect:** A stationary-product project still requires coordination of multiple specialties.
**1. Map the first two eras:** Industry 1.0 is associated with mechanization and steam power. Industry 2.0 is associated with electrical power, assembly lines and mass production.
**2. Map the later eras:** Industry 3.0 uses electronics and computer-controlled automation, including CNC. Industry 4.0 extends this toward connected digital systems and data integration.
**3. Read the complete mapping:** 1.0–Steam Engine, 2.0–Mass production, 3.0–CNC, 4.0–Digitization is the intended pairing.
**Answer: C — 1.0: Steam Engine; 2.0: Mass production; 3.0: CNC; 4.0: Digitization.**
**Convention note:** Digitization began before Industry 4.0. Here the fourth-era label is shorthand for broader digital connectivity and integration, rather than the claim that digital technology first appeared then.
A: **Incorrect:** It places steam power in the fourth era and CNC in the first.
B: **Incorrect:** It reverses the intended third- and fourth-era outcomes.
C: **Correct:** It follows the intended historical sequence across all four eras.
D: **Incorrect:** It reverses the early eras and places CNC in the fourth instead of the third.
When will of the following scenarios, a facility layout problem is relevant?
6406536374109.
A new facility is added
6406536374110.
A new product is introduced
6406536374111.
A new service is introduced
6406536374112.
Shift in technology
Published solution
**1. Identify what a layout decision controls:** It determines the physical arrangement of people, equipment, service points, storage and movement paths.
**2. Check each change:** A new facility needs an arrangement; a new product or service can require different flows and resources; a technology change can alter space, access or equipment needs. All four can therefore make layout planning relevant.
**Answer: A, B, C, D — A, B, C and D.**
A: **Correct:** A new facility requires decisions about the placement of its resources.
B: **Correct:** A new product may need new processing sequences, equipment or storage.
C: **Correct:** A new service can change customer flow and the arrangement of service resources.
D: **Correct:** New technology may require different machines, space, connections and movement paths.